Emerging Tees Valley Joint Minerals and Waste Local Plan Timetable

The Emerging Tees Valley Joint Minerals and Waste Local Plan Timetable can be found here.

Emerging Tees Valley Joint Minerals and Waste Local Plan Timetable

This timetable is published in accordance with Regulation 8 of the Town and Country Planning (Local Planning) Regulations (2026) and shall have effect from the 23rd October 2026. It sets out the timetable for the Emerging Tees Valley Joint Minerals and Waste Local Plan. In accordance with the regulations, the timetable will be reviewed monthly and at key milestones and will be updated, where necessary.

The Tees Valley Joint Minerals and Waste Local Plan is intended to incorporate all of each Council's minerals and waste plan and, when adopted, will replace the current Tees Valley Joint Minerals and Waste Core Strategy Development Plan Document and Polices and Sites Development Plan Document (2011).

The Tees Valley joint Minerals and Waste Local Plan will apply to the administrative areas of Darlington, Hartlepool, Middlesbrough, Redcar and Cleveland and Stockton-on-Tees, excluding land within the North York Moors National Park. 

The Tees Valley Joint Minerals and Waste Local Plan will guide future growth and development of minerals and waste across the five boroughs. It will set out policies on matters relating to the future development minerals and waste on land within the boroughs. Matters that do not relate to minerals and waste will be deal with through each borough’s Local Plan.

Key Stage  Expected Date Actual Date

Notice to Commence made available

(Regulation 19)

23rd October 2026 23rd October 2026

Scoping Consultation – Start date

(Regulation 20)

24th November 2026  To be confirmed

Scoping Consultation – End date

(Regulation 20)

8th January 2026 To be confirmed

Publication of Gateway 1 assessment 

(Regulation 21)

30th April 2027 To be confirmed
Plan Preparation Period 31st May 2027 – 30th March 2029 To be confirmed

Local Plan Content and Evidence Consultation – Start date

(Regulation 23)

17th September 2027  To be confirmed

Local Plan Content and Evidence Consultation – End date

(Regulation 23)

29th October 2027 To be confirmed

Gateway 2 – observations and advice sought

(Regulation 26)

30th November 2027 To be confirmed

Proposed Local Plan Consultation – Start date

(Regulation 27)

15th October 2028  To be confirmed

Proposed Local Plan Consultation – End date

(Regulation 27)

10th December 2028 To be confirmed

Gateway 3- observations and advice sought

(Regulation 31)

30th March 2029 To be confirmed

Submission to SoS for Examination

(Regulation 34)

30th April 2029  To be confirmed

Adoption

(Regulation 39)

31st October 2029 To be confirmed

Date of last review – 23rd October 2026

Schedule of Amendments

The following table sets out the changes that have been made to the timetable since it was first published. 

Detail of Amendment Date of Amendment
N/A N/A

Copies of the timetable are also available on request by:

The timetable is also available to download below:

This data is provided under Open Government Licence